Prepare for the CPIM Exam. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


Which of the following best describes scheduling?

  1. The process of tracking inventory levels

  2. The act of creating various types of schedules for operations

  3. A strategic business planning technique

  4. A method for calculating production costs

The correct answer is: The act of creating various types of schedules for operations

Scheduling is fundamentally about the act of creating various types of schedules for operations within a supply chain or production environment. It entails organizing and allocating resources (such as labor, equipment, and materials) to specific tasks over a set period to ensure that production goals are met efficiently and effectively. This process helps manage time and workflow, enabling smoother operations and minimizing delays. Through effective scheduling, companies can optimize their use of resources, balance workloads, and effectively respond to changing demands. It plays a critical role in production planning and inventory management, as achieving timely production schedules directly impacts product availability and customer satisfaction. The other options do not adequately capture the essence of scheduling. Tracking inventory levels focuses on maintaining optimal stock quantities rather than planning operations. Strategic business planning techniques involve long-term goals and strategies, not the immediate organization of tasks. Calculating production costs relates to financial analysis, rather than the temporal management of production activities. Thus, option B encapsulates the core function of scheduling in supply chain management.