Prepare for the CPIM Exam. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What is the planned backlog for day 56 if the previous planned backlog was 7 hours, with planned input of 14 hours and planned output of 15 hours?

  1. -7 hours

  2. 0 hours

  3. 6 hours

  4. 8 hours

The correct answer is: 6 hours

To determine the planned backlog, we can use the formula: **Planned Backlog (Current Day) = Planned Backlog (Previous Day) + Planned Input - Planned Output.** In this scenario: - The previous planned backlog was 7 hours. - The planned input for day 56 is 14 hours. - The planned output for day 56 is 15 hours. So, we can plug these values into the formula: **Planned Backlog (Day 56) = 7 hours + 14 hours - 15 hours.** Calculating that: **Planned Backlog (Day 56) = 7 + 14 - 15 = 6 hours.** This calculation indicates that the planned backlog for day 56 will be 6 hours. It reflects the balance between the input and output activities planned for that day, adjusted for the previous backlog. This result shows that even though there was a positive input, the output exceeded it slightly, resulting in a manageable backlog of 6 hours.