What is the focus of capacity requirements planning (CRP)?

  1. Scheduling employee shifts for maximum productivity

  2. Determining the amount of resources required for production

  3. Tracking the inventory levels of raw materials

  4. Forecasting sales in the coming quarters

The correct answer is: Determining the amount of resources required for production

Capacity Requirements Planning (CRP) primarily focuses on determining the amount of resources, including equipment and labor, that are necessary to meet production demands. This involves analyzing production schedules and aligning them with resource availability to ensure that the organization can efficiently produce goods without overloading capacity or experiencing shortages. By accurately calculating capacity needs, organizations can effectively plan their production processes and optimize resource utilization. Other options, while related to operational aspects, do not encapsulate the main goal of CRP. Scheduling employee shifts directly ties into workforce management rather than resource capacity planning. Tracking inventory levels relates more to Materials Requirement Planning (MRP) than to CRP, as it deals with stock management rather than resource planning. Forecasting sales is essential for overall business planning but does not directly address the capacity needed for production activities.