In the context of project management, CPM is useful for planning and controlling which of the following?

  1. Resource allocation and budgeting

  2. Coordination among team members

  3. Activities involved in completing a project

  4. Marketing strategies for the final product

The correct answer is: Activities involved in completing a project

The correct answer is focused on the activities involved in completing a project because the Critical Path Method (CPM) is specifically designed to help project managers identify the sequence of crucial tasks required to complete a project on time. By determining the longest stretch of dependent activities and measuring how much time each task takes, CPM allows for efficient scheduling and prioritization of tasks, ensuring that deadlines are met. This approach emphasizes understanding how various project activities interconnect and affect one another, allowing for better management of time and resources dedicated to each task. The primary benefit of CPM is the ability to see which activities are critical to project completion and which have some flexibility in scheduling, thus enabling better project control. In contrast, while resource allocation and budgeting are important aspects of project management, they are not the specific focus of CPM. Similarly, coordination among team members is essential for successful project execution, but it is more about communication and teamwork rather than directly planning activities through a scheduling method. Marketing strategies are not relevant to the CPM framework, as it is strictly related to project timelines and task management rather than promoting or selling the final deliverable.