Prepare for the CPIM Exam. Study with flashcards and multiple choice questions, each question has hints and explanations. Get ready for your exam!

Practice this question and more.


In order to standardize measurement across work centers using different units, what is the best measurement to use?

  1. Hours

  2. Dollars

  3. Throughput

  4. Percentage of final unit

The correct answer is: Hours

Using hours as a standardized measurement across work centers that operate with different units is effective because time is a universally applicable metric. It allows for consistent benchmarking and comparison of performance across various processes, regardless of the specific product being manufactured or the individual work center's operational parameters. When measuring output or productivity, utilizing hours enables managers to assess the efficiency of each work center by establishing a common frame of reference. For example, productivity can be compared in terms of units produced per hour, which provides clear insights into performance levels. This commonality is especially important in organizations with multiple processes that might use differing methodologies or units of measurement. In contrast, dollars may vary significantly based on cost structures and pricing strategies, making it difficult to establish a uniform standard across different work centers. Throughput, while important for understanding production capacity, is often contingent upon specific conditions and can differ greatly between work centers, depending on their operational characteristics. Finally, using percentages of a final unit can be less informative, as it may not provide the concrete data necessary for effective comparisons across diverse processes. The universality of hours as a measurement facilitates clarity in performance assessments and operational efficiency across varying work centers.